Building Project Update for 2/10/2026

Published January 27, 2026

Upcoming Activity


Last Week's Activity

2/3/2026 through 2/9/2026

The site remained under snow and ice for the majority of the week.   On Thursday (2/5) a utility crew was onsite in order to disconnect the fire hydrants around the campus from the main water line and FDC.  Yesterday (2/9) the crews were back on site warming up equipment and getting rough grading moving forward again.

One thing you are sure to notice is that starting yesterday (2/9) demolition crews started removing the exterior skin of the building on the side facing Startown Road and the side with the original main entrance.  Once all of the material is removed the exterior will be covered with a Tyvek wrap that will allow crews to access the walls but prevent moisture penetration during construction.

Activity is quickly spinning back up to full speed so I would anticipate a full update next week!