Building Project Update for 10/14/2026
Schedule
Key Dates
10/15/2026: Building A & B wall rough-in complete.
10/15/2026 - 10/16/2026: No water service on the campus while the sewer system is being upgraded.
10/18/2026: Testify Building Tour (1 of 2)
10/31/2026: Building A & B drywall hanging complete.
11/1/2026: Testify Building Tour (2 of 2)
11/9/2026 - 11/11/2026:
11/25/2026: Building C shell will be completed and an access tunnel will be installed.
11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.
2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings. This will remain the construction entrance through the remainder of the construction project.
2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.
Current Activity
Last Week's Activity
10/5/2026 through 10/9/2026
Building "A" - Exterior






Building "A" - Interior








Building "A" - Raked Seating