Building Project Update for 10/28/2026
Published October 28, 2026
Schedule
Key Dates
11/23/2026 - 11/25/2026: Expect the main transfer swap rescheduled to the week of Thanksgiving . NO POWER ON CAMPUS.
11/25/2026: Building C shell will be completed and an access tunnel will be installed.
11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.
2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings. This will remain the construction entrance through the remainder of the construction project.
2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.
11/1/2026 Building Walkthrough Video
Current Activity
Last Week's Activity
10/19/2026 through 10/23/2026
Building "A" - Exterior




Building "A" - Interior
Main Parking Area











Sewer Upgrade
Building "B" - Exterior
Roof Drain Connection
Building "C"