Building Project Update for 11/4/2026

Published November 4, 2026

Schedule

Key Dates

11/23/2026 - 11/25/2026: Expect the main transfer swap rescheduled to the week of Thanksgiving .  NO POWER ON CAMPUS.

11/25/2026: Building C shell will be completed and an access tunnel will be installed.

11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.

2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings.  This will remain the construction entrance through the remainder of the construction project.

2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.


Current Activity


Last Week's Activity

10/26/2026 through 10/30/2026



Building "A" - Exterior

Building "A" - Interior

Wide interior view of a commercial building under construction, showing exposed metal framing, temporary lighting, concrete floors, and two red scissor lifts.The interior of a building under construction shows exposed metal wall framing, a concrete ledge, and temporary lights hanging from the black ceiling.A long, dark hallway inside a building under construction. The walls are exposed metal studs and the concrete floor leads to a bright doorway at the far end.Interior of a building under construction with exposed metal stud frames for walls, partial drywall, and tools scattered on the concrete floor.An unfinished building interior with metal studs framing the walls and ceiling. A concrete floor has bundles of studs and coiled wires lying on it.A long, curved hallway inside a building under construction, showing exposed metal stud framing for walls and an unfinished ceiling with pipes and wiring.The interior of a building under construction, showing metal stud framing for walls, an exposed ceiling with joists, and a concrete floor with materials.The interior of a building under construction, with metal stud framing forming rooms on a concrete floor. The ceiling is open with wiring visible.A low-angle view of the metal framework for tiered seating inside an auditorium under construction. Unfinished drywall and exposed insulation are visible.The interior of a room under construction, showing exposed metal wall studs, wood blocking, and a network of PVC and copper pipes for plumbing.An unfinished room with metal wall studs. Exposed copper and PVC pipes and electrical wiring run through the open framework, with red wood blocks for support.The interior of a commercial building under construction, showing metal stud wall framing, wood blocking, and rough-in plumbing and electrical work.A construction site with exposed metal wall studs, wood blocking, and plumbing pipes. Cardboard boxes and metal parts sit on the dusty concrete floor.Interior of a building under construction. Metal stud framing and red wooden supports form a wall with rough-in plumbing for multiple toilets or urinals.Interior view of a wall under construction with exposed metal studs, red wood blocking, and various PVC and copper pipes for plumbing and electrical rough-in.

Main Parking Area

A large construction site on a sunny day, with heavy machinery paving a new parking lot. The foreground shows red dirt with tire tracks.

Sewer Upgrade

Building "B" - Exterior

Building "C"