Building Project Update for 7/22/2026

Published July 21, 2026

Project Schedule

Key Dates

8/15/2026: Children's "expansion" remodel to be completed with Temporary Certificate of Occupancy in place.

8/15/2026: Building A: overhead rough-in complete.

9/1/2026: Building A: Stadium seating framing complete.

9/6/2026: Existing construction entrance moves to the rear of the main building.

9/6/2026: Children's addition (Building C) grading and concrete slab work begins.

10/15/2026: Building A & B wall rough-in complete.

10/31/2026: Building A & B drywall hanging complete.

12/2026: Entrance reverts to the old lobby double doors (where it stays for the duration) and feeds thru a tunnel to the side area where the current construction entrance is located.  Work continues in all areas of the building with the exception of the existing sanctuary.


Current Activity


Last Week's Activity

7/13/2026 through 7/17/2026




Building "A" Steel Work

Kid's Area Renovation