Building Project Update for 9/16/2026
Published September 15, 2026
Schedule
Key Dates
10/15/2026: Building A & B wall rough-in complete.
10/31/2026: Building A & B drywall hanging complete.
11/25/2026: Building C shell will be completed and an access tunnel will be installed.
11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.
2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings. This will remain the construction entrance through the remainder of the construction project.
2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.
Current Activity
Last Week's Activity
9/7/2026 through 9/11/2026
Building "A"
Exterior







Interior










Building "B"
Interior
Building "C"