Building Project Update for 9/23/2026

Published September 23, 2026

Schedule

Key Dates

10/15/2026: Building A & B wall rough-in complete.

10/31/2026: Building A & B drywall hanging complete.

11/25/2026: Building C shell will be completed and an access tunnel will be installed.

11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.

2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings.  This will remain the construction entrance through the remainder of the construction project.

2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.



Current Activity


Last Week's Activity

9/14/2026 through 9/18/2026



Building "A" - Exterior

Building "A" - Interior

Wide shot of the interior of a large warehouse under construction. Workers are present, with steel framing, scissor lifts, and temporary lighting visible.

Building "B" - Interior

Building "C"