Building Project Update for 9/23/2026
Published September 23, 2026
Schedule
Key Dates
10/15/2026: Building A & B wall rough-in complete.
10/31/2026: Building A & B drywall hanging complete.
11/25/2026: Building C shell will be completed and an access tunnel will be installed.
11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.
2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings. This will remain the construction entrance through the remainder of the construction project.
2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.
Current Activity
Last Week's Activity
9/14/2026 through 9/18/2026
Building "A" - Exterior
Building "A" - Interior

