Building Project Update for 2/17/2026
Upcoming Activity
Stormwater structures continue being placed. We initially anticipated all stormwater structures being placed last week but will push into next week due to inclement weather.
The grading crew will continue with poor soil removal and put back.
In the North Parking Lot we are awaiting the installation of a piece of conduit. It will allow Duke to move forward with the lighting installation. Scheduling is pending conduit installation. The grading crew will install the conduit when they have a break in rough grading because grading the pad is a significantly higher priority.
We are waiting for the contract from Duke Power for the remaining street lights along the entrance and loop road.
They will also work on detention pond structures if the weather allows .
A meeting is scheduled on Tuesday with the concrete contractor to discuss footing sequencing and scheduling.
Last Week's Activity
1/26/2026 through 1/30/2026
Grading crew was able to resume installation of storm sewer structures and piping in the upper parking area. (3 men)
Clear-site demo crew began demo on EFIS and stone on the front of the existing building. (5 men)
Snow melted away with rising temperatures. Highs in the low 50s with clear skies.
Grading crew continued with storm sewer installation. (4 men)
Demo crew continued with the demo of EFIS and stone. (5 men)
A Pre-Con was held to go over job expectations and to answer any initial questions for the project.
Weather conditions - High near 70. Clear skies.
Demo crew continued with EFIS removal. (5 men)
The grading crew continued with storm sewer installation. (4 men)
Weather conditions - Cloudy with a chance of rain. Temps in the morning were low 40s with an afternoon high in the 50s.
Demo crew continued with EFIS removal. (5 men)
The grading crew continued with storm sewer installation. (4 men)
Weather conditions - Cloudy with a chance of rain. Temps in the morning were right around freezing with afternoon highs in the 50s.
Grading crew removed poor soil in the building pad area. (4 men)
The demo crew removed the roof overhang, decking, and support beams. (7 men)
Weather conditions - sunny with morning lows near freezing and afternoon highs near 60.
Demo crew completed EFIS demo and installed plastic and Tyvec moisture barrier. (5 men)
Weather conditions - clear and sunny with morning lows near freezing and afternoon highs near 60.