Handicap Lot Update (11/13/2025)

Thank you to all who responded with the names of their folks who may need to use the new handicap parking lot. We will make sure those folks get the information they need to make use of that lot.
As you can see in the images below the "heavy duty" later of the asphalt was placed last Friday. The remaining area will have asphalt but it will be the thinner "standard duty" material.
This week we will have surveyors onsite and mark up all the areas where concrete will be placed. Next week we anticipate the concrete curb and gutters placed. The remaining asphalt will be put down after the concrete. We aren't sure how Thanksgiving will impact the schedule. We anticipate the lot being ready around the first or second Sunday in December. Either way, once we are confident the lot will be ready we will make sure it is communicated through this email and our other communication channels.