Building Project Update for 3/17/2026
Upcoming Activity
Grading was essentially delayed for one week due to wet weather.
Pad work complete with the exception of a few loads of dirt. When you look out at the area now you are seeing the final grade of the soil. Add several inches of gravel and several inches of concrete on top of that and you will be at the final gate of the building floor.
Rough grading on the admin wing pad is expected to start next week.
Footer installation will begin next week if the weather allows. These will be the large, rebar reinforced, concrete anchors that will support the steel bones of the building.
You will see them being built two to three at a time throughout the building area.
The final piece of conduit should be installed in the north parking lot this week. Once that is installed Duke Power can be contacted and the installation can be scheduled.
Cabling for the street lights along the entrance and loop road has continued being installed. Installation is expected to be complete in the next week or two.
The retention pond has been a low priority as the pad has been prepared for main portion of the building project.
We can expect work to be starting back up in two weeks, once the admin wing pad has been prepped.
Last Week's Activity
3/9/2026 through 3/13/2026
No work was completed due to wet conditions.
⅝ inch of rain fell Sunday night. Monday's weather conditions were overcast in the morning with skies clearing in the afternoon. Temperatures in the mid to high 70s.
The survey crew was on-site, laying out the edge of slab and column lines for the worship center and administration wing. (2 men)
No grading due to wet soil conditions.
Weather conditions were sunny with temperatures in the high 70s.
The grading contractor performed grading in some of the dryer areas. (1 man).
The weather was partly cloudy with temperatures in the 70s.
No workers on-site.
¾ inch of rain fell throughout the day.
Lake Electric installed a temporary power panel for worker access.