Building Project Update for 7/29/2026

Published July 28, 2026

Project Schedule

Key Dates

8/15/2026: Children's "expansion" remodel to be completed with Temporary Certificate of Occupancy in place.

8/15/2026: Building A: overhead rough-in complete.

9/1/2026: Building A: Stadium seating framing complete.

9/6/2026: Existing construction entrance moves to the rear of the main building.

9/6/2026: Children's addition (Building C) grading and concrete slab work begins.

10/15/2026: Building A & B wall rough-in complete.

10/31/2026: Building A & B drywall hanging complete.


Current Activity


Last Week's Activity

7/20/2026 through 7/24/2026




Building "A" Steel Work

Building "B" Steel Work

Kid's Area Renovation