Building Project Update for 7/29/2026
Published July 28, 2026
Project Schedule
Key Dates
8/15/2026: Children's "expansion" remodel to be completed with Temporary Certificate of Occupancy in place.
8/15/2026: Building A: overhead rough-in complete.
9/1/2026: Building A: Stadium seating framing complete.
9/6/2026: Existing construction entrance moves to the rear of the main building.
9/6/2026: Children's addition (Building C) grading and concrete slab work begins.
10/15/2026: Building A & B wall rough-in complete.
10/31/2026: Building A & B drywall hanging complete.
Current Activity
Last Week's Activity
7/20/2026 through 7/24/2026
