Building Project Update for 8/5/2026

Published August 4, 2026

Project Schedule

Key Dates

8/15/2026: Children's "expansion" remodel to be completed with Temporary Certificate of Occupancy in place.

8/15/2026: Building A: overhead rough-in complete.

9/1/2026: Building A: Stadium seating framing complete.

9/6/2026: Existing construction entrance transitions to the rear of the main building.

9/6/2026: Children's addition (Building C) grading and concrete slab work begins.

10/15/2026: Building A & B wall rough-in complete.

10/31/2026: Building A & B drywall hanging complete.

11/25/2026: Building C shell will be completed and an access tunnel will be installed.

11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.

2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings.  This will remain the construction entrance through the remainder of the construction project.

2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.


Clarification...It Won't Be Silver

I have had a question posed countless times over the last few weeks.  It never fails...a person who seems either confused or irritated asks me "so is the building going to be silver?"

Ok...fair enough, it looks silver.

The current skin the structure is being wrapped with is part of the exterior wall, but it is an internal component.  As you will see in the pictures in the "Building A" section there are actually several layers to the exterior walls.  Eventually all of the layers will be covered with "cladding" materials to create the final facade that matches the existing building. The white stone and wood cladding will be used as accent elements.

Currently between the Discipleship Building and the Kid's area we have a sample wall with the cladding materials.  This represents the materials you can expect to see installed over the silver walls.  Please note that the materials selected very closely match the cladding on the existing building.

While I am happy to keep explaining this over and over...feel free to share this information with everyone.

An outdoor sample wall showing various construction materials, including a stacked stone base, white stone panels, stucco, and two colors of wood-look siding.

Current Activity


Last Week's Activity

7/27/2026 through 7/31/2026




Building "A" Steel Work

Building "B" Steel Work

Kid's Area Renovation