Building Project Update for 8/12/2026
Project Schedule
Key Dates
8/15/2026: Children's "expansion" remodel to be completed with Temporary Certificate of Occupancy in place.
8/15/2026: Building A: overhead rough-in complete.
8/30/2026: The last Sunday the kid's ministry will be using the original kid's hallway and associated classrooms.
8/30/2026: The last Sunday using the current construction entrance.
9/1/2026: Building A: Stadium seating framing complete.
9/6/2026: Existing construction entrance transitions to the rear of the main building.
9/6/2026: Children's addition (Building C) grading and concrete slab work begins.
10/15/2026: Building A & B wall rough-in complete.
10/31/2026: Building A & B drywall hanging complete.
11/25/2026: Building C shell will be completed and an access tunnel will be installed.
11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.
2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings. This will remain the construction entrance through the remainder of the construction project.
2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.
Current Activity
Last Week's Activity
8/3/2026 through 8/7/2026
Building "A"
Exterior


Building Transition







Interior
Framing (Production Hallway)
Stadium Seating Structure
Building "B"
Exterior
Interior
Renovation
Kid's Area
Exterior Work