Building Project Update for 8/19/2026

Published August 18, 2026

Project Schedule

Key Dates

8/30/2026: The last Sunday the kid's ministry will be using the original kid's hallway and associated classrooms.

8/30/2026: The last Sunday using the current construction entrance.

9/1/2026: Building A: Stadium seating framing complete.

9/6/2026: Existing construction entrance transitions to the rear of the main building.

9/7/2026: Children's addition (Building C) grading and concrete slab work begins.

10/15/2026: Building A & B wall rough-in complete.

10/31/2026: Building A & B drywall hanging complete.

11/25/2026: Building C shell will be completed and an access tunnel will be installed.

11/25/2026: Rear construction entrance returns to the current location but using the access tunnel will be required.

2/1/2026: The tunnel entrance will shift to a new construction entrance that utilizes the main corridor between the existing and new buildings.  This will remain the construction entrance through the remainder of the construction project.

2/1/2026: The temporary construction lobby and original kids area will be closed for remodeling.


Current Activity


Last Week's Activity

8/10/2026 through 8/14/2026



Building Walkthrough for 8/16/2026


Building "A"

Exterior

A large building under construction with purple exterior sheathing. A yellow JCB telehandler is in the foreground on a dirt lot under a partly cloudy sky.
A long commercial building under construction, its exterior walls covered in bright purple sheathing panels. The site is dirt with materials scattered around.

Building Transition

A construction site showing a new steel-framed building with purple exterior sheathing being built next to an existing tan building, with a worker on site.

Interior

The interior of a large steel-frame building under construction, with workers installing insulation into the walls and large rolls of material on the ground.

Building "B"

Exterior

Renovation

Exterior Work