Building Project Update for 2/3/2026
Upcoming Activity
Stormwater structures continue being placed. We initially anticipated all stormwater structures being placed last week but will push into next week due to inclement weather.
Rough grading continues on pace and on schedule. Anticipate completion at the end of February or early March.
In the North Parking Lot we are awaiting the installation of a piece of conduit. It will allow Duke to move forward with the lighting installation. Scheduling is pending conduit installation. The grading crew will install the conduit when they have a break in rough grading because grading the pad is a significantly higher priority.
We are waiting for the contract from Duke Power for the remaining street lights along the entrance and loop road.
The retention pond was anticipated to be completed this week but was delayed due to inclement weather. Work can resume once crews can safely access the area.
Last Week's Activity
1/26/2026 through 1/30/2026
No workers on-site due to winter storm over the weekend that dropped over an inch of ice. Weather conditions-Morning temps in the low teens with highs around freezing. Ground still covered with ice.
No workers on-site. Ice is still covering the ground. No melting due to low temperatures. Weather conditions- Morning lows in the low teens with daily high in the mid 30s.
No workers on-site. Some melting today, but the majority of the area is still covered with ice. Some of the parking lots are clearing up. Weather conditions- Morning lows in the low 20s with highs around 40.
Enviro-pond was onsite to cap off the fire hydrant located in the construction area. (2 men)
No workers on-site. Conditions at the site remain unfavorable for work.